Amery Rail awarded Harrow Weald DC Sub Station Project – Groundworks Package

 

AMCO has awarded the Groundworks Package to Amery Rail to execute the following activities:

 

  • Provision of various mechanical excavators to reduce levels for new base slabs
  • Site clearance and muck away
  • Assistance to screw fast pile installation
  • Construction of new HV and DC module RC Slabs
  • Installation of new service ducts
  • Installation of new troughs
  • Construction of new RC columns to support new modules
  • Construction of new safe routes / stairways
  • Construction of new brick walls

 

The above works commenced in March 2011 and are being executed adjacent to the west coast main line.

 

 